1303 MW Lumut CCGT Power
Plant in Malaysia
Engineering, Construction,
Commissioning & Operation Experience
Miro R. Susta, IMTE AG, Switzerland Ahmad Jauhari Yahya, Malakoff Bhd., Malaysia Zulkifli Ibrahim, Teknik Janakuasa Sdn. Bhd., Malaysia
Arab Electricity 1997, Manama, Bahrain March 1997 |
Abstract |
From 1994 to 1997 five Independent Power Producer projects, totaling 4070
MW, have been completed in Peninsula Malaysia, providing 38% of the total
current generating capacity in the country. The 1303 MW Lumut Combined Cycle Gas Turbine (CCGT) Power Plant is the largest among
Malaysian IPPs.
Lumut CCGT is not only the
largest power plant in Malaysia, but also the largest CCGT in South-East
Asia and the third largest IPP in the world.
After completion in 1997,
each block will deliver 651.7 MW to TNB national grid and shall achieve an
efficiency of above 52 % at local tropical ambient conditions.
Its design has been geared
towards high efficiency, reliability and availability paying a great deal
of attention to environmental considerations.
Lumut CCGT consists of two
identical blocks, each comprising three dual fuel gas turbines, three heat
recovery steam generators and one condensing steam turbine. Engineering, Procurement and Construction contract for supply
of 1303 MW Lumut CCGT was signed between Segari Energy Ventures Sdn. Bhd.
(subsidiary of Malakoff Berhad) and ABB Power Generation Sdn. Bhd. in
December 1993.
After having obtained all
licenses and after signing power purchase, fuel supply and financing
agreements, SEV released the instruction to proceed in April 1994.
The first CCGT block was
handed over to the local O & M company, Teknik Janakuasa Sdn. Bhd.,
immediately after completion of
performance tests and trial run on 25 May 1996, only 25 months and
25 days from the project official commencement date. At the same day the
block 1 started official commercial operation.
In 1993, SEV contracted
Swiss consulting engineering company,
IMTE
AG, as technical advisor.
IMTE
AG was responsible for providing technical advisory and quality
assurance services during contract negotiations, project engineering,
factory inspections and tests phase as well as for supervision of
erection, commissioning and taking over of equipment.
From 25 May 1996 until 31
August 1996, the first block accumulated 2610 operational hours and has
delivered 1057000000 kWh to Malaysian national grid. It is fully
available for any kind of operation as directed by national load dispatch
center. This paper contains interesting and most practical details gained during project planning and engineering, construction, erection and commissioning phase as well as during initial operation period of Lumut CCGT. |
Authors
(Status
1998) |
Miro R. Susta |
Director |
IMTE AG Power Consulting Engineers |
Switzerland |
Ahmad Jauhari Jahya |
Managing
Director |
Malakoff Berhad |
Malaysia |
Zulkifli Ibrahim (Co-Author) |
Chief Operating Officer |
Teknik
Janakuasa Sdn. Bhd. |
Malaysia |
© IMTE AG